Project Summary

This project consisted of full abatement and demolition of 3 floors which spanned approximately 20,000 Sqft each and the complete removal and disposal of 20,000 Sqft of roofing materials.  The roofing materials included gravel, multiple felt layers and 12” thick light weight concrete.  The demolition and offload were a challenge on this project due to the campus and library remaining open to students and faculty.  A negative airflow was constructed to offload roof debris and asbestos waste directly from the roof into 40 yard dumpsters.

Similar Projects
Employee Portal

Our Website uses cookies. Cookies are small text files held on your computer that help us understand how you use our Website. Our cookies do not store any personal information about you, and you can delete and block cookies via your browser settings at any time. By clicking “Ok” you agree to accept our use of cookies. Learn more by reviewing our privacy policy.