Project Summary

The project at 300 Lakeside was a project for the environmental division that involved the removal and replacement of insulation above-ceiling on fully occupied floors. Each night, Ceilings were opened up in select locations and containments were set up for dust control to allow for removal/replacement work. Due to the building being fully occupied, the floors were returned to the same condition as the night before on a daily basis. In total, approximately 500,000 square feet of insulation were removed and replaced on 20 floors.

Similar Projects
Employee Portal

Our Website uses cookies. Cookies are small text files held on your computer that help us understand how you use our Website. Our cookies do not store any personal information about you, and you can delete and block cookies via your browser settings at any time. By clicking “Ok” you agree to accept our use of cookies. Learn more by reviewing our privacy policy.